Last Updated: 2025-10-30 Overall Progress: 39/137 tasks (28.5%) Current Phase: ✅ Phase 3 - Authentication (Completed)
🎯 Quick Status
| Phase | Status | Progress | Started | Completed |
|---|---|---|---|---|
| 01 Foundation | ✅ Done | 9/10 (90%) | 2025-10-29 | 2025-10-29 |
| 02 Database | ✅ Done | 12/12 (100%) | 2025-10-30 | 2025-10-30 |
| 03 Authentication | ✅ Done | 18/18 (100%) | 2025-10-30 | 2025-10-30 |
| 04 Products | ⏳ Todo | 0/10 (0%) | - | - |
| 05 Cart | ⏳ Todo | 0/12 (0%) | - | - |
| 06 Checkout | ⏳ Todo | 0/15 (0%) | - | - |
| 07 Payment | ⏳ Todo | 0/12 (0%) | - | - |
| 08 Order Processing | ⏳ Todo | 0/15 (0%) | - | - |
| 09 ERP Integration | ⏳ Todo | 0/10 (0%) | - | - |
| 10 i18n | ⏳ Todo | 0/8 (0%) | - | - |
| 11 Testing & Deployment | ⏳ Todo | 0/15 (0%) | - | - |
Legend: ⏳ Todo | 🔄 In Progress | ✅ Done | 🚫 Blocked | ⏭️ Skipped
🚀 Current Work
Phase: Phase 3 - Authentication ✅ COMPLETED
Tasks Completed (18/18):
- ✅ Install nuxt-auth-utils + jose
- ✅ Configure Cidaas environment variables in .env
- ✅ Add Cidaas config to nuxt.config.ts runtimeConfig
- ✅ Create PKCE generator utility (server/utils/pkce.ts)
- ✅ Create Cidaas API client utility (server/utils/cidaas.ts)
- ✅ Create JWT validation utility (server/utils/jwt.ts)
- ✅ Create /api/auth/login.post.ts endpoint
- ✅ Create /api/auth/callback.get.ts endpoint
- ✅ Create /api/auth/register.post.ts endpoint
- ✅ Create /api/auth/logout.post.ts endpoint
- ✅ Create /api/auth/me.get.ts endpoint
- ✅ Create useAuth composable (composables/useAuth.ts)
- ✅ Create LoginForm component (components/Auth/LoginForm.vue)
- ✅ Create RegisterForm component (components/Auth/RegisterForm.vue)
- ✅ Create auth page with tabs (pages/auth.vue)
- ✅ Create auth middleware (middleware/auth.ts)
- ✅ Create rate-limit middleware (server/middleware/rate-limit.ts)
- ✅ Test OAuth2 flow end-to-end and document authentication flow
Next Steps:
- Begin Phase 4 - Products (Display & List):
- Read
tasks/04-products.md - Create product API endpoints (/api/products/index, /api/products/[id])
- Build ProductCard and ProductList components
- Create ProductDetail page
- Implement product image handling
- Test product display and queries
- Read
📅 Timeline
Week 1 (Target)
- Phase 1: Foundation ✅ COMPLETED 2025-10-29
- Phase 2: Database ✅ COMPLETED 2025-10-30
- Phase 3: Authentication
Week 2 (Target)
- Phase 4: Products
- Phase 5: Cart
- Phase 6: Checkout
Week 3 (Target)
- Phase 7: Payment
- Phase 8: Order Processing
- Phase 9: ERP Integration
Week 4 (Target)
- Phase 10: i18n
- Phase 11: Testing & Deployment
- MVP Launch 🎉
🚧 Blockers
None currently. All blockers resolved.
📝 Decisions Needed
None currently.
✅ Completed Milestones
- Planning & Documentation (PRD, Architecture, Tech Stack)
- Docker Development Setup (docker-compose.dev.yml)
- Task Management System Setup
- Phase 1 - Foundation (2025-10-29)
- Nuxt 4 project initialized
- shadcn-nuxt and Tailwind CSS configured
- TypeScript strict mode enabled
- ESLint and Prettier configured
- Basic project structure created
- Development server tested successfully
- Phase 2 - Database (2025-10-30)
- Drizzle ORM installed and configured
- All 6 database tables defined (users, products, carts, cart_items, orders, order_items)
- Relations configured correctly
- Initial migration generated and applied successfully
- Database connection utility created
- CRUD operations tested and verified
- Drizzle Studio setup and working
- Comprehensive schema documentation added
- Phase 3 - Authentication (2025-10-30)
- nuxt-auth-utils and jose packages installed
- Cidaas OAuth2/OIDC configuration completed with environment variables
- PKCE generator utility implemented for secure authorization code flow
- Cidaas API client utility created with token exchange and user info functions
- JWT validation utility implemented using jose library with JWKS
- All 5 authentication endpoints created and tested
- useAuth composable built with login, logout, register functions
- LoginForm and RegisterForm components created with full validation
- Auth page with tabbed interface implemented
- Auth middleware for protected routes functional
- Rate limiting middleware configured (5 attempts/15min for login, 3 attempts/1hr for register)
- OAuth2 flow tested end-to-end with proper session management
- Complete authentication documentation with flow diagrams
📊 Phase Details
Phase 1: Foundation (Nuxt 4 Setup)
Status: ✅ Done | Progress: 9/10 (90%)
Tasks:
- Initialize Nuxt 4 project with pnpm
- Install shadcn-nuxt module
- Configure Tailwind CSS v4
- Setup TypeScript strict mode
- Configure ESLint + Prettier
- Setup Git hooks (⏭️ Skipped - deferred to Phase 11)
- Create basic folder structure
- Configure nuxt.config.ts
- Create basic layout components
- Test development server
Note: Docker services not started (requires manual action). All other tasks completed successfully.
Details: tasks/01-foundation.md
Phase 2: Database (Drizzle ORM)
Status: ✅ Done | Progress: 12/12 (100%)
Tasks:
- Install Drizzle ORM & PostgreSQL driver
- Configure drizzle.config.ts
- Create users table schema
- Create products table schema
- Create carts & cart_items schema
- Create orders & order_items schema
- Generate initial migration
- Apply migrations to dev DB
- Create database connection utility
- Test CRUD operations
- Setup Drizzle Studio
- Document schema decisions
Completed: 2025-10-30
Phase 3: Authentication (Cidaas OAuth2)
Status: ✅ Done | Progress: 18/18 (100%)
Tasks:
- Install nuxt-auth-utils + jose
- Create PKCE generator utility
- Create Cidaas API client
- Create JWT validation utility
- Implement /api/auth/login endpoint
- Implement /api/auth/callback endpoint
- Implement /api/auth/register endpoint
- Implement /api/auth/logout endpoint
- Implement /api/auth/me endpoint
- Create useAuth composable
- Create LoginForm component
- Create RegisterForm component
- Create auth page with tabs
- Create auth middleware
- Create rate-limit middleware
- Test OAuth2 flow end-to-end
- Test session management
- Document authentication flow
Completed: 2025-10-30
Details: tasks/03-authentication.md
Phase 4: Products (Display & List)
Status: ⏳ Todo | Progress: 0/10 (0%)
Tasks:
- Create /api/products/index.get.ts endpoint
- Create /api/products/[id].get.ts endpoint
- Create ProductCard component
- Create ProductList component
- Create ProductDetail page
- Create products index page
- Add product images handling
- Test product display
- Optimize product queries
- Document product schema
Phase 5: Cart (Shopping Cart)
Status: ⏳ Todo | Progress: 0/12 (0%)
Tasks:
- Create /api/cart/index.get.ts endpoint
- Create /api/cart/items.post.ts endpoint
- Create /api/cart/items/[id].patch.ts endpoint
- Create /api/cart/items/[id].delete.ts endpoint
- Create useCart composable
- Create CartItem component
- Create CartSummary component
- Create cart page
- Test cart operations
- Add cart persistence
- Optimize cart queries
- Document cart logic
Phase 6: Checkout (Forms & Flow)
Status: ⏳ Todo | Progress: 0/15 (0%)
Tasks:
- Create checkout schema (Zod)
- Create CheckoutForm component
- Create AddressForm component
- Implement address pre-fill from user profile
- Create /api/checkout/validate endpoint
- Create checkout page
- Implement save address to profile
- Add form validation (VeeValidate)
- Test checkout flow
- Test address save/load
- Add error handling
- Optimize checkout UX
- Add loading states
- Test mobile checkout
- Document checkout logic
Phase 7: Payment (PayPal Integration)
Status: ⏳ Todo | Progress: 0/12 (0%)
Tasks:
- Install PayPal SDK
- Configure PayPal credentials
- Create /api/payment/paypal/create.post.ts endpoint
- Create /api/payment/paypal/capture.post.ts endpoint
- Create /api/payment/paypal/webhook.post.ts endpoint
- Integrate PayPal button on checkout
- Implement payment success flow
- Implement payment error handling
- Test PayPal sandbox
- Add payment status tracking
- Document PayPal integration
- Test webhook handling
Phase 8: Order Processing (BullMQ + X-API)
Status: ⏳ Todo | Progress: 0/15 (0%)
Tasks:
- Install BullMQ + ioredis
- Configure Redis connection
- Create order queue
- Create order worker
- Create X-API client utility
- Implement transformOrderToXAPI function
- Implement submitOrderToXAPI with retry
- Create /api/orders/index.post.ts endpoint
- Create /api/orders/[id].get.ts endpoint
- Test queue processing
- Test X-API submission (mock)
- Add error handling & logging
- Setup BullBoard dashboard
- Test retry logic
- Document order processing
Details: tasks/08-order-processing.md
Phase 9: ERP Integration (NAV Product Sync)
Status: ⏳ Todo | Progress: 0/10 (0%)
Tasks:
- Create NAV ERP product schema (Zod)
- Create /api/erp/products.post.ts endpoint
- Implement API key authentication
- Implement product validation
- Implement product upsert logic
- Add error handling & logging
- Test product sync (mock data)
- Test API key auth
- Add rate limiting
- Document ERP integration
Details: tasks/09-erp-integration.md
Phase 10: i18n (Internationalization)
Status: ⏳ Todo | Progress: 0/8 (0%)
Tasks:
- Install @nuxtjs/i18n
- Configure i18n module
- Create locale files (de-DE.json, en-US.json)
- Translate all UI strings
- Create language switcher component
- Test route localization
- Test currency/date formatting
- Document i18n structure
Phase 11: Testing & Deployment
Status: ⏳ Todo | Progress: 0/15 (0%)
Tasks:
- Setup Vitest for unit tests
- Write tests for auth utilities
- Write tests for API endpoints
- Setup Playwright for E2E
- Write E2E test: user registration
- Write E2E test: complete checkout flow
- Create Dockerfile (production)
- Create docker-compose.yml (production)
- Configure GitLab CI/CD
- Test production build
- Setup staging environment
- Deploy to staging
- Final QA on staging
- Document deployment process
- Deploy to production 🚀
Details: tasks/11-testing-deployment.md
📈 Progress Over Time
| Date | Overall Progress | Phase | Notes |
|---|---|---|---|
| 2025-01-29 | 0% | Planning | Task system created |
| 2025-10-29 | 6.6% | Phase 1 - MVP | ✅ Foundation completed: Nuxt 4, shadcn-nuxt, Tailwind CSS, ESLint, Prettier all configured |
| 2025-10-30 | 15.3% | Phase 2 - MVP | ✅ Database completed: Drizzle ORM, all tables defined, migrations applied, Studio working, schema documented |
| 2025-10-30 | 28.5% | Phase 3 - MVP | ✅ Authentication completed: OAuth2/OIDC with PKCE, JWT validation, auth endpoints, UI components, middleware |
🎉 Next Steps
- Start Phase 4: Products (Display & List)
- Read
tasks/04-products.mdfor detailed tasks - Create /api/products/index.get.ts endpoint with product listing
- Create /api/products/[id].get.ts endpoint for single product details
- Build ProductCard component with responsive design
- Build ProductList component with filtering/sorting
- Create ProductDetail page
- Implement product image handling (CDN/storage)
- Test product display and optimize queries
- Read
Let's build this! 🚀